Frequently asked questions


We answer some of the most frequently asked questions about the Hornsea 3 Offshore Wind Farm.  

  • Why does an offshore wind farm have to lay cables onshore – why can’t they be laid offshore instead?

    We need to lay onshore export cables to connect the green energy generated offshore by the wind farm to the National Grid’s main substation in Norwich. Without the onshore cables, the renewable energy generated offshore could never reach homes or businesses. 

     Before deciding on our cabling route, we undertook a route planning exercise that included extensive consultation which considered technical, engineering, and environmental aspects. 

    As a result of that consultation, we determined the 51 km underground cable route from Weybourne to Norwich.  

    Read the full Hornsea 3 FAQ document here

  • Why are you digging up the countryside?
    We’re laying the cabling that will bring energy onshore from our offshore wind farm once it’s built. That requires 51 km of cables to be buried underground onshore. We have agreements in place with landowners on how and where we work. Once cables have been laid, we’ll make good all construction sites and carefully restore the land to how it was before. 
  • What will happen to the land once you’ve dug it up and laid the cables?
    We work hard on the preservation and control of the topsoil during the construction process to ensure that once works have finished, we’re able to restore the land to how it was before. After we’ve dug the trenches and buried cables, we put them back neatly with the original material and topsoil. We replant vegetation and restore everything to the way we found it, working in cooperation with the landowner. This is called reinstatement. 
  • What’s going on in Oulton and Swardeston?

    We’ve begun to build the onshore part of Hornsea 3.  We are currently laying the cables that will bring the energy generated offshore by Hornsea 3 and connect it to our onshore electricity substation in Swardeston, near Norwich, Norfolk.  

    From there, the energy will be connected to the National Grid so it can be distributed to millions of homes across the UK. So far, we’ve laid about 6 km of cable out of a total of 51 km, so we’re still in the early stages. 

    We’ve also been doing some work on our onshore substation including landscaping. And we’re preparing the land for the battery energy storage system.  

  • Why do such large lorries have to go along such small roads?

    As this is such a large national infrastructure project, traffic, and deliveries to and from the sites are unavoidable. But we’ve been working closely with local authorities and residents to give advance notice of works taking place to help minimise disruption.

    Explore our latest construction information

  • How will local residents benefit from this project?

    Norfolk is becoming a key hub for green energy, which will bring long-term investment and jobs to the region. We’ve launched our Hornsea 3 Community Benefit Fund which commits £7 million (£700,000 every year for the next ten years) to projects developed by, and for the benefit of, the local community in the North Norfolk and East Anglia region. We are committed to making a positive impact in the communities where we construct and operate our offshore wind farms.   

    Learn more about our Hornsea 3 Community Benefit fund 

  

Contact information icon

Contact us

Please feel free to reach out to members of our team with questions anytime.


Email: community@hornsea3.co.uk

Telephone: 0800 158 2354